E2 Express Changes as Plan Deviations and Signals

On this page

Describe the Change before Acting

“Material is late” describes an event. A planner also needs the affected orders, operations, quantities and periods. Link the event to business objects before selecting a response.

The teaching periods T1, T2 and T3 are in chronological order. Consider this event: material M was expected in T2 and is now confirmed for T3. Operation OP-1 needs it in T2. First inspect its task quantities and possible alternatives, then describe the planning impact.

Distinguish Four Records

Record Purpose Information in this example
Business change Updated fact M's arrival time and source
PlanBias Impact relative to the plan Objects, periods, direction and quantities
PlanSignal Route impact to a recipient Receiving capability, priority and proposed direction
Follow-up measure Execution or pending confirmation Release adjustment, proposed objective change, rule or coordination

The table explains the business meaning of each record. When calling an interface, use its documented types and fields for the selected version.

Follow the Linkage Recipe

The planning_system_linkage orchestration recipe performs planning and analysis before the impact_analysis action. Follow the planning analysis in production_analysis.planning, the linkage report in planning_system.linkage_report, and the plan_biases and plan_signals records to trace how the same business change is handled.

PlanBias is produced during execution and is managed separately from the standard input tables in data.db. For long-term storage, save it in the application's result records with the source-data version and run identifier.

Keep the Decision between Signal and Action

A deviation may lead to monitoring, reduced near-term release, a proposed objective change or a purchasing check. Record the proposal, approval and actual handling separately so participants know who acts next.

Review the analysis output, recipient, adoption status and processing result in order. After an objective change is adopted, check the actual configuration and rerun. Until then, retain it as a proposal awaiting confirmation.

Aggregate without Losing Traceability

One delay may affect several orders. Aggregation supports prioritization, but preserve the path from order to operation, material and period. If availability later recovers, distinguish updated records so the impact is not counted twice.

Exercise and Suggested Answer

For the teaching event, identify affected objects, information sources, two possible measures and their approvers. Write an accurate statement when no measure has yet been executed.

For example: material risk has been identified for operation OP-1 in T2, and a proposed release-time change awaits the planning owner's confirmation. After execution, record the actual released tasks, timing and planning results to evaluate the measure.

Further Reading

Planning and Scheduling · Results and Feedback · Component Responsibilities

Worksheets: Worksheet: Operational Rule and Verification · Worksheet: Review and Change Record

Topic E · Previous: From the Master Plan to Work Release and Scheduling · Next: Define the Scope of a Disruption Response