B3 Align Time, Capacity and Material Availability

On this page

“Capacity Is Available Today” Needs a Definition

A shift has 480 minutes, existing work uses 25%, and maintenance needs 30 minutes. How much remains? Check whether the 480 minutes already excludes maintenance, what the percentage uses as its denominator, and whether maintenance overlaps existing work.

For this hand-calculated teaching example, 480 minutes is gross shift time, the 25% is measured against it, and maintenance does not overlap existing work. Remaining time is 480 × (1−0.25) −30 = 330 minutes. This calculation applies to those assumptions; other capacity definitions require the corresponding conversion.

In the standard interface, this normal period has scale=28800 seconds and status=1. Combine existing work and maintenance as used=(120+30)/480=0.3125. Available time is then 28800×(1−0.3125)=19800 seconds, or 330 minutes. Maintenance is already included in that fraction and is not deducted again.

Align Four Kinds of Time

Information Related object Check
Order due time order_item.delivery_time Resolves to a time unit
Resource availability capacity and shift/calendar data Scope, scale and reductions are defined
Material availability kitting_information.time_unit Arrival timing and quantity units are clear
Plan output planning_result.time_unit Uses the same time axis as inputs

time_unit.id is a reference identifier, offset expresses relative sequence, and scale is the period length in seconds. Interpret actual time positions using the origin and period sequence; consecutive identifiers alone do not represent days or minutes.

Keep Ratios, Quantities and Time Separate

capacity.used is the occupied or unavailable fraction between zero and one: 25% is 0.25. Neither 25 nor 120 minutes expresses the same field meaning. Storage, calculation and percentage display need a consistent convention. This input fraction is distinct from resource utilization calculated from a plan.

Condition Review
Shifts already produce net capacity Check whether maintenance was already deducted
Parallel stations are included in capacity Avoid multiplying station count again
Materials arrive tomorrow Align arrival with the consuming operation, not just total demand
Results are needed in minutes Establish the native unit and conversion first

Inspect a DecisioWorks Case

Read the time, capacity, material-availability and result tables. Select one work center and one time unit, then trace the related orders and materials. Inspect specific periods and key materials as well as total spare capacity to find shortages hidden by averages.

Use a data copy for changes. Modify one confirmed maintenance arrangement, inspect the capacity-generation rule and data difference, then run the corresponding planning capability. Review that period's load, waiting and unmet demand rather than relying on average utilization.

Exercise and Suggested Answer

Under the 330-minute assumptions, a new task requiring 360 minutes leaves a 30-minute shortfall. Check whether additional time or another resource can be approved. Also inspect uninterrupted-processing requirements and maintenance windows so that any added time is actually usable for the task.

If the original 480 minutes already excluded maintenance, the calculation would be wrong. Keep the result together with its definitions so another reader can reproduce it under the same assumptions.

Further Reading

Standardized Data Interface · Data Objects and Fields · Data Readiness and Validation · ERP and MES Data Mapping

Worksheets: Worksheet: Scenario and Decision Task

Topic B · Previous: Process Routes and Operation-Level BOMs · Next: Distinguish Facts, Constraints and Preferences