Injection molding: inspect the sequence after changing weights

Color, product attributes and job order interact. A higher score or a larger weight only becomes meaningful when you examine the actual sequence and changeover counts.

Recorded 2026-08-31 · DecisioWorks v1.4.0 · Commercial Enterprise license · API records, not a live run on this page

The business question

How can changeover preferences be expressed when different products run consecutively? This example compares sequences after adjusting color- and container-capacity-related weights. It shows how to inspect trade-offs, rather than assuming that one adjustment will improve every measure.

Input: how product attributes enter scheduling

Main objects in this sample
ObjectCount or attributesWhat it tells us
Demand37 recordsProducts and quantities to schedule
Work centers2Resource structure
Materials115 recordsMaterial objects and relationships
Process-adaptor relationships418 recordsCompatibility between operations and resources
Product attributesColor, cap type, container capacityChangeover differences; container capacity is a product attribute
Run configurationWork center 2; 40 positions × 3 cycles120 sequence positions in total

Configuration: change preferences, retain comparison conditions

Constraints and weights used in this comparison
SettingBaselineAdjusted
Capacity, demand and inventory constraintsEnabledUnchanged
Sequence and circular changeover constraintsEnabledUnchanged
Color-related weight0.10.8
Container-capacity-related weight11.5
Solver resources16 threads / 60-second limitUnchanged

The system reads attributes and compatibility relationships, builds constraints and objectives, and returns a sequence with analysis results. Keep both configurations and outputs. Compare physical changeover counts first, then examine weighted evaluation terms.

Output: what did this re-run show?

Baseline and re-run from the same API comparison
MeasureBaselineAdjusted
Valid candidates returned11
New result rows120120
Sequence changeovers4146
Circular changeovers614
Weighted changeover cost14.966.4
Total API request time66.57 seconds66.50 seconds
Action events / errors12 / 012 / 0

In this recorded comparison, changeover counts increased after the weights were raised. A feasible plan found within the available resources is not necessarily a proven global optimum. Scores calculated under different weights are also not an improvement percentage. Review sequences, business measures and constraint satisfaction together.

What should the next comparison change?

  • Identify the changeover type you want to reduce and confirm attribute meanings and units.
  • Hold data and runtime resources constant; compare one preference change at a time.
  • Inspect adjacent jobs and cycle transitions to locate the changes.
  • Consider delivery, output and shop-floor conditions before keeping the result, adjusting again or returning to the baseline.