Standardized Data Interface
09 Interpret Results and Prepare the Next Planning Cycle
Task: Recover Business Meaning from Operation Results
This is a manually constructed candidate for calculation, not solver
output. The base database keeps planning_result empty;
candidate rows are stored separately in CSV.
| workcenter | time_unit | process | number |
|---|---|---|---|
| 11 | 1 | 1001 | 80 |
| 12 | 1 | 1002 | 80 |
| 11 | 2 | 1001 | 40 |
| 12 | 2 | 1002 | 40 |
Resolve each operation to its route and product. Assembly is the final operation, so deliveries correspond to 80 and 40. The four rows total 240 operation-output units, not 240 finished deliveries.
Recover Time and Material Usage
| Period and resource | Output | Units/cycle | Cycles | Seconds/cycle | Processing minutes |
|---|---|---|---|---|---|
| Day-one stamping | 80 | 4 | 20 | 600 | 200 |
| Day-one assembly | 80 | 1 | 80 | 120 | 160 |
| Day-two stamping | 40 | 4 | 10 | 600 | 100 |
| Day-two assembly | 40 | 1 | 40 | 120 | 80 |
Consumption is 80 blanks and 160 fasteners on day one, then another 40 and 80. Check cumulative consumption against cumulative supply. With opening finished stock 20 and issues 80 then 40, ending finished inventory is 20 on both days.
These calculations assume no initial setup, changeovers, scrap, or
additional OEE adjustment. Add applicable time from the adopted records
and rules when checking real results. Read value_1/2/3
using the scenario's definition; cycle number and sequence position are
scenario-specific interpretations.
A Maintenance Change
Extending day-one stamping maintenance from two to three hours
reduces available time from 360 to 300 minutes. The 200-minute stamping
load still fits in aggregate. If maintenance occurs at the start of the
shift and all 80 units needed on day one must finish stamping before any
assembly starts, with no overlap between operations, continuous
execution needs 180+200+160=540 minutes, exceeding eight
hours. The two-hour-maintenance version needs 480 minutes.
Transferring all 80 units together is an additional assumption, not a
consequence of batch_size=20. Confirm the processing batch
and transfer batch separately. If each completed batch of 20 can move to
assembly, with no transport or setup losses and both machines able to
operate concurrently, the four batches finish at minutes 270, 320, 370,
and 420. The 420-minute and 540-minute calculations use different
transfer rules; neither is a solver run.
A resource-load check therefore does not establish that the entire operation chain fits within the shift. Transfer batches, overlapping production, or changed windows need explicit scenario rules and model support. Result review needs both aggregate quantities and operation-level detail.
Prepare the Next Input
- Separate executed, committed, and adjustable work; retain the original plan.
- Update remaining demand using actual deliveries, rather than planned completion.
- Update available materials using actual consumption, receipts, and blocked quantities.
- Carry forward necessary resource commitments without counting maintenance twice.
- When the planning origin moves, rebuild every time reference, not just result numbering.
- Record configuration differences before starting the next capability run.
Exercise and Answer
Day one promised 80 but delivered only 60. If the cumulative commitment is unchanged, day-two remaining delivery is 60: the original 40 plus backlog 20. This does not automatically mean 60 new units must be produced. Review finished stock, work in process, completed but undelivered quantities, and inventory policy. Treating delivery backlog as new production can duplicate output.